Reviewing and planning a council depot redevelopment

Independent review of a depot feasibility study, then writing the Project Initiation Document for the redevelopment.

Introduction

Dacorum Borough Council runs waste collections, waste transfer, street cleansing and grounds maintenance from its Cupid Green depot, a 1940s former military site. The depot is at capacity, does not meet modern accessibility standards and cannot support an electric fleet. Around 21,000 new homes (32% growth) are planned over two decades.

The Council had prepared a feasibility report internally, and its Senior Leadership Team wanted the findings independently tested before committing to investment. From March 2025 to June 2026, Nik acted as Lead Adviser, providing waste operations and infrastructure expertise.

Project details

Nik carried out an independent critical review of the Council’s feasibility report, including a site visit and engagement with neighbouring councils and the county council. The review agreed that Cupid Green was the best site: the Council owns it, it has planning precedent as a depot, and it was the lowest-risk and quickest to deliver.

The review also raised points the report had not fully tested, including where waste could be tipped, whether the local grid could support electric vehicles, and whether single-bodied vehicles would suit the Council better than its twin-pack vehicles. Nik presented the findings to Elected Members in September 2025, then authored the Council’s Project Initiation Document.

Recircle’s input

Nik’s support to the Council included:

  • Critically reviewing the Council’s depot feasibility report and authoring a report on the review
  • Visiting the site and engaging neighbouring councils, the county council and Hemel Garden Communities
  • Assessing site options, including the one alternative site
  • Advising on waste transfer and tipping options
  • Advising on fleet electrification, and on twin-pack versus single-bodied vehicles
  • Presenting findings to Elected Members
  • Setting up project governance and authoring the Project Initiation Document
  • Preparing the programme, risk register and outline cost estimate, including briefing cost consultants

Outcomes

Preferred site confirmedthe independent review agreed with the Council’s choice of Cupid Green
£40m outline estimatecentral cost estimate for the redevelopment, within a £30–60m range
Next stage proposedthe Project Initiation Document recommended approval of RIBA Stage 2 concept design